Activities
Each month there will be 1 local / regional activity within the project.
1.project logo contest - month 1
2.creation and updating of the project website, duration 1-24 months
3. coordinating online project management meetings - months 3,7,10,14, 17, 20
4. organization of training workshops after returning from mobility - months 5, 9, 12, 16,19, 22
5.organization of Erasmus project presentation sessions - months 2, 22
6. Coordination of the Creative Recycling Guide, duration 1-24 months, writing and publishing module 1 entitled “Creative
Recycling” - month 6
7. Dissemination of information - throughout the project
8.2 press releases for the launch and completion of the project
9.creation of promotional materials
10. Other events - throughout the project
1.project logo contest - month 1
2.creation and updating of the project website, duration 1-24 months
3. coordinating online project management meetings - months 3,7,10,14, 17, 20
4. organization of training workshops after returning from mobility - months 5, 9, 12, 16,19, 22
5.organization of Erasmus project presentation sessions - months 2, 22
6. Coordination of the Creative Recycling Guide, duration 1-24 months, writing and publishing module 1 entitled “Creative
Recycling” - month 6
7. Dissemination of information - throughout the project
8.2 press releases for the launch and completion of the project
9.creation of promotional materials
10. Other events - throughout the project